Concrete driveway replacement, widened to the fence, with rebar and drains
Location
Montclair, San Bernardino County
Home type
Single-story home with a two-car garage, a front lawn, and a side yard
Timeline
May 28 to June 3, 2025, plus a tree trim on June 7
Materials
Concrete with rebar, broom finish, saw-cut joints, PVC drain lines
Scope
Demo, excavation, drainage, forms, pour, finish, joints, tree trim

About This Project

Three Surfaces, One New Slab

This single-story Montclair home has a two-car garage, a front lawn on the left, and a red wood fence down the right side of the lot. Between the lawn and that fence, the yard was three different surfaces: an old concrete driveway about as wide as the garage door, a strip of dirt and loose rock out to the fence, and a side yard of more dirt running back to the gate.

Old gray driveway curving into the lawn, with square pavers by the palm planter, before the new concrete, Montclair
Before: the old driveway, its edge curving into the lawn.
Strip of dirt and loose rock between the old driveway and the fence, before Hybrid Renovations replaced it, Montclair
Before: dirt and loose rock out to the fence.
Side yard by the red wood gates before the job: bare dirt, loose rocks, and a broken square of old concrete, Montclair
Before: the side yard by the red gates.

The job was to turn those three into one. After a site check on May 27, 2025, the final change order set it at 1,000 square feet of new concrete with rebar, plus rain drainage: from a straight edge along the lawn to the fence, and back through the side yard to the gate.

1,000 square feet of new concrete, with rebar
7 days from the first day on site to the finished slab
1 front-yard tree kept and trimmed, not removed

What changed at the site check

The first write-up, on May 23, had a tree coming out of the front yard, roots and all. The final change order kept it: the tree was trimmed instead, on June 7, as the last item on the job. The same change order wrote rebar into the slab.

Demo, drains, and forms

On May 29 a skid steer broke out the old driveway. By the next day the front yard was dug down to dirt from the lawn to the fence, and the old square pavers by the palm planter were pulled up and stacked out of the way.

Skid steer on the old driveway on demo day, with the Hybrid Renovations yard sign on the front fence, Montclair
During: May 29, the old driveway coming out.
Front yard dug out to dirt in front of the two-car garage, with white PVC drain lines and fittings by the gate, Montclair
During: May 30, dug out, with the drain lines laid.

The drainage went in before any concrete. White PVC drain lines run along the fence and out toward the street gate, laid in the open ground while every fitting was easy to reach. Then the forms went in, and the forms are where the new shape was decided: where the old driveway curved into the lawn, the new edge runs straight, and on the right the boards sit tight to the fence line.

Crew member setting a form board along the red wood fence, a white PVC drain line in the dug-out ground, Montclair
During: setting forms along the fence.
Cutting form boards with a circular saw beside PVC drain pipe along the fence, on a Hybrid Renovations job, Montclair
During: cutting form boards beside a drain line.
Round drain grate set flush in the new slab beside a brick pillar, where the side yard meets the driveway, Montclair
After: the drain grate by the brick pillar.

A drain in the slab

Where the side yard meets the driveway, a round drain grate sits flush in the new concrete beside the brick pillar, set level with the surface so water runs in instead of sitting at the pillar.

Salvador Lopez, lead project manager at Hybrid Renovations
Rebar doesn't keep concrete from cracking. No driveway is crack-proof. What rebar does is hold the pieces together if a crack ever opens, so one side can't drop or lift away from the other. The saw cuts tell the slab where to crack, and the rebar keeps it level if it does.
SalvadorProject Manager

The finish and the lines

The new slab was poured and finished by June 3. A broom pulled across the fresh surface leaves the fine texture you can see up close, which gives shoes and tires some grip in the rain. The straight lines between the panels are saw cuts.

Why the lines are there

Concrete shrinks a little as it cures, and that pull has to go somewhere. Control joints, cut part of the way into the fresh slab, give it a planned weak line. If the slab cracks, the crack follows the cut, where it's hard to see, instead of wandering across the middle of a panel.

New concrete through the side yard from the driveway to the back gate, between the brick wall and the red fence, Montclair
After: the side yard to the back gate.
Broom-finished panels up to the garage door and brick pillar, a palm in a barrel planter, by Hybrid Renovations, Montclair
After: up to the garage door.
New concrete running along the fence line to the street gate, saw-cut into even panels by Hybrid Renovations, Montclair
After: along the fence to the street.

Build log

Contract to finished slab in 11 days

  • Fri, May 23

    Contract signed A new driveway with rain drainage.

  • Tue, May 27

    Site check Final change order: 1,000 sq ft with rebar, the tree trimmed.

  • Thu, May 29

    Demo A skid steer breaks out the old driveway.

  • Fri, May 30

    Dug out Drain lines laid, forms set along the lawn and fence.

  • Tue, Jun 3

    Slab finished Broom finish, saw cuts, the yard taped off to cure.

  • Sat, Jun 7

    Tree trim The last item on the change order.

Project specs

Area
1,000 sq ft of new concrete
Layout
Lawn edge to the fence, plus the side yard to the back gate
Slab
Concrete with rebar
Finish
Broom finish
Joints
Saw-cut control joints
Drainage
PVC drain lines and a round drain grate
Removed
The old driveway and the square pavers by the planter
Crew
Licensed concrete subcontractor, managed by Hybrid Renovations
Wide new driveway by Hybrid Renovations seen from the garage, saw-cut panels running out to the iron gates, Montclair
After: the new driveway, garage to street.

Montclair has plenty of front yards like this one: a driveway about as wide as the garage, with dirt filling in the rest. We see the same layout in Upland, Ontario, and Claremont, and the same answer works there: break out the old slab, set the drainage first, and replace it all with one new concrete driveway from edge to edge.

The service behind this project

Planning a New Concrete Driveway?

  • Licensed and insured, CSLB #1085596
  • Workmanship warranty

Frequently asked questions

Thinking about a project like this?

If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.

Yes. One way is to pour a new strip beside the old slab and tie it in with steel dowels, but new concrete rarely matches the color and texture of old, so the seam stays visible. The other is to break out the old driveway and pour the full width new, which is what this Montclair job did: one slab and one broom finish from the lawn to the fence. Some cities and HOAs cap how much of a front yard can be paved, so those rules come before the new width is set.

Many driveways are poured without it, using wire mesh or no steel at all. Rebar doesn't keep concrete from cracking, and no driveway is crack-proof, but if a crack opens, the steel holds the two sides tight and level so one can't drop or lift. On this Montclair driveway, rebar was written into the final change order for all 1,000 square feet.

Mostly by slope. California's residential code says hard surfaces within 10 feet of a house must slope at least 2 percent away from it, so rain runs off instead of pooling at the foundation. Where water can't run to the street, a drain grate in the slab and pipe underneath carry it away, and that pipe has to go in before the pour. On this Montclair job, PVC drain lines were laid along the fence before the pour, and a round grate sits flush in the slab by the side yard.

It's the texture left by pulling a stiff broom across the concrete while it's still fresh: a pattern of fine ridges across the surface. Those ridges give shoes and tires grip when the slab is wet, and the National Ready Mixed Concrete Association recommends a broom finish on outdoor concrete for better traction. A smooth troweled surface looks sleeker but gets slick in the rain. Every panel of this Montclair driveway has a broom finish.

Still have questions?

Mon–Sun · 7 AM – 7 PM

FREE ESTIMATE

Get Your Free Estimate

We come to your home, look at the project, and give you a free, written estimate with no obligation. Construction, remodeling, and renovations across Los Angeles and Orange County.

  • Licensed and insured, CSLB #1085596
  • Free, whether or not you hire us
  • Same-day scheduling available
  • Measured on site, priced in writing
(562) 903-3955

Prefer to call? We answer 7 AM – 7 PM, Mon–Sun.

Tell us about your project