TEX-COTE COOLWALL Repaint of a Sun-Facing Stucco Home in Glendora
November 2025
Glendora
A full exterior recoat of a single-story stucco home. We waterblasted the walls, patched more than fifty hairline cracks, trenched the coating past grade, and primed, then finished in TEX-COTE COOLWALL Tailored Tan 0239 with Hint of Vanilla trim.
Exterior repaint with TEX-COTE COOLWALL heat-reflective coating system
Location
Glendora, Los Angeles County
Home type
Single-family, single-story stucco home with attached garage
Timeline
February 2026, about two weeks across several visits
Materials
TEX-COTE COOLWALL Tailored Tan 0239, Trim-Cote Hint of Vanilla 0001
Scope
Stucco repair, fascia replacement, repaint, garage doors, shed, vents
About This Project
A Sun-Beaten Stucco Home, Recoated to Take the Heat
This Glendora home had spent years facing the afternoon sun on tired, cracked stucco. We recoated the exterior with the TEX-COTE COOLWALL system, a heat-reflective coating built to hold its color in the heat, and finished it in Tailored Tan with vanilla trim.
Before: Chalky, faded stucco with hairline cracks running across the body and eaves.
What the waterblast uncovered
Once the chalk was washed off, the wall told the real story: more than fifty hairline cracks across the stucco, and an old coating that had stopped right at the dirt line, leaving a weak seam where the wall met the soil.
How the COOLWALL system went on
1Wash and patch. We waterblasted the walls and eaves, then filled more than fifty hairline cracks with Flex-Patch, each one feathered flush so it disappears under the topcoat.
2Trench at grade. We trenched three to six inches down where the soil meets the foundation, so the coating runs past grade instead of stopping in a weak line at the dirt.
3Prime. Twenty gallons of Hi-Reflective Primer went on next, the bonding base the COOLWALL system needs before any color.
4Topcoat and trim. Then COOLWALL in Tailored Tan 0239 across the stucco, with Trim-Cote in Hint of Vanilla 0001 on the trim, fascia, and wood at a semi-gloss for crisp edges.
50+cracks patched
44gallons applied
42squares coated
Materials used
TEX-COTE COOLWALL
KYNAR IR
Tailored Tan 0239
Hint of Vanilla 0001
Hi-Reflective Primer
Flex-Patch
After: The finished front elevation in Tailored Tan with Hint of Vanilla trim.
After: Garage door and gable coated, trim picked out in vanilla.
After: New fascia, vents, and eave line carried into the same finish.
COOLWALL is a system, not a coat of paint. It only performs if the surface under it is sound and primed right, so we patch, trench, and prime before any color. Prep is where this finish lives or dies.
Leonardo · Project Manager
Why COOLWALL holds up to the Glendora sun
COOLWALL carries KYNAR infrared pigment. Rather than letting the wall soak up solar heat the way standard latex does, the manufacturer reports the pigment reflects much of it back, so the surface runs cooler and holds its color longer. On a wall that faces the afternoon sun, that is the whole point.
February weather did not cooperate. Rain pushed the crew off the walls more than once, so we ran the work across about two weeks of dry windows rather than rush a coat onto a wet surface. The finished home holds an even Tailored Tan body, crisp vanilla trim, a matched shed, and a coating made for the sun it faces. This is part of our residential exterior coating work across Los Angeles County, including nearby Azusa, San Dimas, and Covina.
The service behind this project
Looking for an exterior painting contractor in Los Angeles County?
If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.
Most exterior repaints of a single-story home this size run about seven to ten working days. This one stretched across roughly two weeks because February rain kept pulling the crew off the walls, and we will not coat over a wet surface. We schedule around dry windows so the coating cures the way it should.
COOLWALL is a coating system, not a single coat of paint. It carries KYNAR infrared pigment, which the manufacturer reports reflects much of the sun's heat back off the wall instead of letting the stucco soak it up, so the surface runs cooler and holds its color longer. On this home it went on over a Hi-Reflective Primer after full crack repair, which is how the system is meant to be applied.
Yes, and that is most of the work. On this project we waterblasted the walls, patched more than fifty hairline cracks with Flex-Patch, and replaced about fifty feet of soft fascia before any color went on. Coating over failing wood or open cracks only hides a problem for a season, so we fix the surface first.
Only on dry days. A coating has to go on a dry surface, so we never roll it over wet stucco. On this Glendora home, February rain pushed the crew off the walls more than once, and the work ran across about two weeks of dry windows instead of rushing a coat onto a damp wall.
A project manager visits your home, measures, and helps you plan the work around your budget. Free, no-obligation estimates for construction, remodeling, and renovations across Los Angeles and Orange County.
Thanks for reaching out. Our team will be in touch within one business day to schedule your home visit.
TALK TO A PROJECT MANAGERSpeak With a Real Project Manager
Have a project in mind or need to think it through? Talk it over with a dedicated project manager who can answer questions and walk you through your options, with no pressure.
Thanks for reaching out. A project manager will call you back within one business day to talk through your project. No pressure, and no obligation.A project manager will call you to talk through your questions and concerns. No pressure and no obligation.
ASK US ANYTHINGHave a Question? We're Happy to Help.
Ask about your project, our services, timelines, or anything else. A real, local representative will get back to you, with no obligation and no pressure.
Thanks for reaching out. A real, local person will get back to you within one business day with an answer. No obligation.Ask anything, big or small. A real person on our local team will get back to you, with no obligation.
FREE IN-HOME CONSULTATIONBook Your Free Consultation
A project manager comes to your home, measures, and looks at what's actually there before quoting anything. You get a written price before they leave. No obligation, anywhere in Los Angeles or Orange County.
We've got your request. A project manager will reach out within one business day to book your visit.The consultation is free with no obligation. We will call to confirm the details and find a time that works for you.