Roof replacement with a full re-deck over skip sheathing
Location
Whittier, Los Angeles County
Home type
Single-story home with a detached two-car garage
Timeline
February 2026, three days on the roof
Materials
OSB sheathing, synthetic underlayment, gray architectural shingles, R-38
Scope
Tear-off, re-deck, underlayment, shingles, flashing, vents, attic R-38

About This Project

One Layer Off, Then the Boards Showed Through

This single-story Whittier home came to us with one layer of worn three-tab shingles on the house and its detached garage: faded tan, the granules worn thin, and chimney flashing held together with tar. The homeowners signed on a Wednesday in February. By the following Monday, both roofs were new, 22 squares in all, on a brand-new deck.

Faded tan 3-tab shingles with worn granules and old pipe vents on the main slope before the replacement, Whittier
Before: faded 3-tab with the granules worn thin.
Spaced skip-sheathing boards exposed on the garage roof after the old shingles came off, by Hybrid Renovations, Whittier
Tear-off: spaced boards under the old shingles.

Under the old shingles, the boards had gaps between them.

That's skip sheathing: one-by boards nailed across the rafters with open space between them. It's how roofs here were framed when wood shakes were common, because shakes need air underneath. Asphalt shingles need the opposite. They want a solid surface under every inch, so each nail bites wood and each course lies flat.

The last roof had gone on right over the gaps. That works for a while. Then the nails that missed a board start to back out, and the shingles between the boards begin to dip.

Shingle over the boards again, or deck the whole roof first?

Considered

New shingles straight onto the spaced boards, the way the last roof went on. Faster, but nails land in air, the courses can dip between boards, and shingle makers want a solid deck under their product.

Chosen

OSB sheathing over every board on the house and the garage, nailed into the rafters, before a single shingle went on.

Why: It's the only way every nail holds and the roof stays flat for its whole life, and it's what the installation instructions call for.

Salvador Lopez, lead project manager at Hybrid Renovations
You could see light between those boards from the attic. You can't nail a new roof into air, so we sheathed every square, the garage too. Then the roof went on the way it should have the first time.
SalvadorProject Manager
Crew member in a Hybrid Renovations shirt tearing off the old shingles on the detached garage roof, Whittier
Tear-off: the garage roof coming off.
Full roof plane covered in new OSB sheathing nailed over the original spaced boards during the re-deck, Whittier
During: OSB over the spaced boards.
Brick chimney standing on the new OSB roof deck with the old flashing removed, ready for new flashing, Whittier
During: the chimney on the new deck.

The chimney, reflashed

What we found

Old metal flashing at the chimney base, patched over the years with tar and caulk, the seams opening at the corners.

What we did

Pulled it all, then set new step flashing under the shingles and new counter flashing into the brick, in gray to match the roof.
Chimney base with old flashing patched in tar and caulk, before Hybrid Renovations reflashed it, Whittier
Before: tar and caulk at the chimney base.
New ridge cap and gray flashing at the brick chimney on the finished roof, by Hybrid Renovations, Whittier
After: new flashing and ridge cap at the chimney.

With the deck solid, synthetic underlayment went down over the whole roof that same Saturday, so the house was dried in before the crew left. The new shingles are architectural: two layers laminated together, which gives the roof its depth and holds up to wind far better than the single-layer three-tab that came off. New vent caps and pipe flashings went in as the courses reached them.

R-38 in the attic, the same week

With the roof finished, we blew R-38 loose-fill insulation across the attic floor. ENERGY STAR recommends R-30 to R-60 for attics in Southern California's climate, and R-38 sits right in that range.

Build log

Signed Wednesday, roofed by Monday

  • Wed, Feb 4

    Contract signed The house, the detached garage, and the attic.

  • Thu, Feb 5

    Measured 16 squares on the house, six on the garage, one layer of composition shingles.

  • Sat, Feb 7

    Tear-off and new deck Old roof off, OSB over the spaced boards, synthetic underlayment down by evening.

  • Mon, Feb 9

    Shingles and ridge The supplier's truck came without the ridge caps. They arrived later that day, the ridge went on, and the roof was done.

  • Thu, Feb 12

    Final walkthrough House, garage, and attic, with the homeowners.

Project specs

Roof area
22 squares: house 16, detached garage 6
Removed
One layer of 3-tab composition shingles
Deck
OSB sheathing over the original spaced boards
Underlayment
Synthetic, the whole roof
Shingles
Architectural asphalt, gray blend
Hip and ridge
Matching ridge cap shingles
Chimney
New step and counter flashing
Vents
New vent caps and pipe flashings
Attic
R-38 loose-fill insulation
Finished slope of gray architectural shingles with straight courses up to the ridge cap, by Hybrid Renovations, Whittier
After: the finished slope, eave to ridge.

We replace roofs all over Whittier and the cities around it, including La Habra, Pico Rivera, and Santa Fe Springs, where our office is. Plenty of homes here were first roofed in wood shakes, so spaced boards under the old shingles are something we plan for, not something that surprises us. See more of our roof replacement work.

The service behind this project

Looking for a roofing contractor in Los Angeles County?

  • Licensed and insured, CSLB #1085596
  • Workmanship warranty

Frequently asked questions

Thinking about a project like this?

If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.

No. Skip sheathing is spaced boards meant for wood shakes, and asphalt shingles need a solid deck so every nail lands in wood and every course lies flat. Shingle makers' installation instructions call for a solid deck, so we cover the boards with OSB or plywood first. On this Whittier home we sheathed all 22 squares, house and garage.

Most single-story homes take two to four days on the roof. This one, 16 squares on the house and six on the garage with a full re-deck, ran from Saturday to Monday. The number of layers, deck repairs, and weather set the pace.

It's a good time, because the crew and the access are already there. ENERGY STAR recommends R-30 to R-60 for attics in Southern California, and this home got R-38 loose-fill. A well-insulated attic keeps more summer heat out of the rooms below.

Yes, and we recommend it when both roofs are the same age. Here the detached garage's six squares got the same deck, underlayment, and shingles in the same visit, so the two roofs match and wear at the same rate.

Still have questions?

Mon–Sun · 7 AM – 7 PM

FREE ESTIMATE

Get Your Free Estimate

We come to your home, look at the project, and give you a free, written estimate with no obligation. Construction, remodeling, and renovations across Los Angeles and Orange County.

  • Licensed and insured, CSLB #1085596
  • Free, whether or not you hire us
  • Same-day scheduling available
  • Measured on site, priced in writing
(562) 903-3955

Prefer to call? We answer 7 AM – 7 PM, Mon–Sun.

Tell us about your project