1930s-Style Bathroom Remodel with Yellow Tile in Fullerton
June 2026
Fullerton
A 2000s remodel had stripped the 1938 character out of this Fullerton bath. We took out the beige tile and espresso vanity, tiled a cast-iron tub alcove in butter-yellow, and laid a hex mosaic floor.
Full bathroom remodel in a 1930s style, tub alcove rebuilt and tiled
Location
Fullerton, Orange County
Home type
Single-story 1938 Spanish Revival bungalow, its only bathroom
Timeline
June 2026, 18 working days on site
Materials
Butter-yellow 4x4 tile, black trim, 1-inch hex mosaic, cast-iron tub
Scope
Demo to studs, plumbing, waterproofing, tile, console sink, sconces
About This Project
Eighteen Days Inside a 1938 Bathroom
28%moisture behind clean tile
11original 1938 tiles found
18working days
Nothing in this bathroom looked broken. The grout was clean, the vanity was solid, the tub drained. Then Salvador Lopez, our lead project manager, pressed a moisture meter to the bottom row of tile above the tub, and it read 28 percent.
Before: the mid-2000s remodel, from the doorway.
After: the tub, toilet, and sink in the same spots.
This is the only bathroom in a 1938 Spanish Revival bungalow. A mid-2000s remodel had given it tan paint, beige tile with a mosaic band, an espresso vanity, and diagonal floor tile. It worked, but it could have been in any 2005 tract home. The homeowners wanted a bathroom the house would recognize.
Build log
Eighteen days at a glance
Week 1
Open it up. Dust wall, tile and greenboard off, a joist under the tub repaired.
Week 2
Rough-in. Copper lines, cast-iron tub on a ledger, new subfloor, blocking. Rough inspection passed.
Week 3
Waterproof and tile. KERDI-BOARD, window wrap, wall tile and trim, then the hex floor.
Week 4
Finish. Console sink, shower set, sconces, glass door knob, paint. Final inspection passed.
Day 1: Testing a room that looked fine
Before anything comes off a wall, we test it. Salvador metered the tile above the tub, tapped every floor tile, and checked the joists from the crawlspace. The tub wall was wet behind clean grout. Two floor tiles in front of the tub sounded hollow. Neither shows in a photo, and both changed the plan.
Day 2: What the beige tile was hiding
Before: beige tile, a mosaic band, a straight rod.
After: cast iron, tiled to the ceiling.
What we found
The 2000s tile sat on greenboard, a paper-faced drywall, with no membrane behind it. Water had wicked into the bottom 10 inches of the board, which crumbled by hand at the tub flange.
What we did
We took the alcove to the studs, covered all three walls and the alcove ceiling in Schluter-KERDI-BOARD, banded every seam, and lapped the membrane over the tub flange. The tile stops an eighth of an inch above the tub, and that gap gets silicone, never grout.
The shortcut we didn't take
Tiling over the old greenboard would have saved most of a week. It would also have sealed a wet wall behind brand-new tile.
Behind the board was the original plaster, and on it, 11 butter-yellow tiles and a strip of black cap that the last crew never scraped off. We matched a glossy 4x4 to them from three samples, held up in the homeowners' own window light, not a showroom's.
We'd gone back and forth on colors for months. Then Salvador handed us a yellow tile from inside our own wall.
Renee S. · Homeowner, Fullerton
Days 3 and 4: Straight walls, a heavy tub
The 1938 studs were half an inch out of plumb, and the galvanized supply lines had scaled to half their bore. We ran new copper back to the main and shimmed every stud to a straightedge, because 4x4 tile on a crooked wall shows it in every grout line.
The new 60-inch cast-iron tub weighs about 300 pounds empty. In the crawlspace, the joist under its drain end had been notched halfway through for an old trap. We sistered a new 2x8 to it before four of us set the tub on a 2x4 ledger screwed into the studs, so its flange can't drop away from the caulk.
Day 5: Keep the window or close it
A window in a wet wall
Considered
Framing the window in, which makes the tub wall simple to waterproof.
Chosen
Keeping the original opening and wrapping it in membrane.
Why: It's the room's only daylight and part of the 1938 house. Done right, a window in a tiled alcove stays dry.
How the window stays dry
The membrane runs into the window frame, and the sill, finished in black tile, slopes back toward the tub, with silicone where tile meets frame. The old flat sill had held water for years.
Day 7: The floor under the floor
Before: 13-inch tile on the diagonal.
After: hex mosaic, a black border, and flowers.
The two hollow tiles were a symptom: the 1938 plank subfloor flexed underfoot. Big tile can ride that for years; a 1-inch mosaic can't. We glued and screwed 1/2-inch plywood over the planks, then Schluter-DITRA, so the mosaic is uncoupled from what movement is left.
Days 11 to 14: Tile set to a laser line
The wall tile runs to 54 inches around the room under a black bullnose cap, with a thin black liner one row down and a black base at the floor.
Glossy black trim shows everything. If one cap tile sits a hair proud of the next, you see it from the doorway, so the cap went on last, to a laser line.
Salvador Lopez · Lead Project Manager
How the hex floor stays true
1Center lines first. We snapped the room's centers and dry-laid the sheets from the middle out.
2A border off the walls. Two black rows, a few tiles off every wall, stepped around the wing wall.
3Flowers by hand. Six hexes pulled around a white center and replaced with black ones, about ten tiles apart.
Days 16 and 17: A sink that hangs on the wall
Before: espresso, granite, a three-light bar.
After: a console sink between two sconces.
A console sink hangs most of its weight on the wall, so 2x10 blocking went in at basin height during rough-in. The drain and supplies moved to center on the basin, and because the trap is exposed chrome, it had to hang plumb. Two sconce boxes went in 30 inches apart at 66 inches high, either side of an oval mirror.
Day 18: The parts you touch
Before: one lever, two heads on one arm.
After: an exposed chrome riser and rain head.
Behind the cross handles of the exposed chrome shower set sits a pressure-balance valve, so a running kitchen faucet can't scald anyone. The original door stayed, but its 2000s nickel knob came off for a clear glass knob on a bronze plate.
Schluter-KERDI-BOARD walls and ceiling, KERDI-BAND seams
Wall tile
Glossy 4x4 butter-yellow ceramic, black bullnose cap and liner
Floor
1-inch hex mosaic with black flowers and border, over plywood and Schluter-DITRA
Sink
Vitreous china console on two chrome legs, exposed chrome trap
Lighting
Two black sconces with opal glass shades
Window
Existing fiberglass double-hung, black tile surround, sloped sill
After: the original door, now with a glass knob.
The finished bath carries our workmanship warranty in writing. We build bathroom remodels for older homes across north Orange County, including Brea, Placentia, and Anaheim.
The service behind this project
Looking for a bathroom remodeling contractor in Orange County?
If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.
Not where it gets wet. Greenboard is drywall with a water-resistant paper face: it handles humidity, not water running down tile and grout. Building codes stopped allowing it behind tub and shower tile years ago. A wet wall needs a waterproof board or membrane, like Schluter-KERDI-BOARD, with every seam sealed and lapped over the tub.
A hollow tile has lost its bond to the mortar under it, or was never fully bedded. The usual cause is a subfloor that flexes. A few hollow tiles can sit for years, but they tell you the floor moves. Before new tile, we stiffen the floor, often with plywood glued and screwed over old planks, and add an uncoupling membrane.
Often you can get close. An original tile found behind a wall or under a fixture is your reference: compare samples against it in the room's own daylight, because showroom lights shift color. Size, gloss, and edge shape matter as much as the color. We tile whole walls in the new tile rather than patching it beside old tile, where a small difference shows.
Often, yes. Cast iron holds heat, resists scratches, and keeps its enamel for decades, and it suits a period bathroom. It is heavy, about 300 pounds empty for a 60-inch tub, so the joists under it get checked and repaired first, and the tub is set on a ledger screwed to the studs so its rim can't settle away from the caulk.
We come to your home, look at the project, and give you a free, written estimate with no obligation. Construction, remodeling, and renovations across Los Angeles and Orange County.