A La Mirada driveway and front entry rebuilt in Angelus Courtyard Stone: about 1,000 square feet of pavers with a charcoal border, and a sloped paver landing where a plywood ramp used to sit.
Paver driveway, sloped entry landing, and side walk
Location
La Mirada, Los Angeles County
Home type
Single-story home with a two-story wing over the garage
Timeline
August 5 to 19, 2025, about two weeks for the pavers
Materials
Angelus Courtyard Stone in Gray-Charcoal, charcoal border and caps
Scope
Asphalt tear-out, base, pavers, border, entry landing, side walk
About This Project
From a Plywood Ramp to a Paver Landing
In July 2025, the driveway at this La Mirada home was old asphalt, cracked into a web from the street to the walls. At the front door, a sheet of plywood lay over the tiled step as a ramp. We broke out the asphalt, laid about 1,000 square feet of Angelus Courtyard Stone, and built the ramp into the pavers for good.
The plywood came out. The slope stayed.
Before: July 22, plywood over the tiled step.
After: the paver landing and its charcoal cap.
July 2025August 2025
A plywood sheet over a tiled stepA paver landing that slopes to the driveway
Cracked asphalt, street to garageAbout 1,000 square feet of Courtyard Stone
Brick edging and raw asphalt edgesA charcoal border on every edge
Asphalt up to the side wallA paver walk with its own border
A step that needed a ramp
The old entry was a single tiled step at the door, a few inches above the driveway. Somebody had bridged it with plywood, which shifts and soaks up every rain. That sheet told us how the front door gets used, so we didn't plan a new step. We planned a new slope.
Step or slope at the front door?
Considered
A plain paver step, like the tiled one.
Chosen
A long paver landing along the wall: a full step at the door that tapers down until it meets the driveway at the far end.
Why: The landing sits right under the threshold at the door. At the far end there's no step at all, so a cart, a stroller, or a wheelchair rolls straight on.
That sheet of plywood was the brief. We kept the slope it made and built it in pavers, so there's a full step at the door, you're level with the driveway at the far end, and nothing underfoot shifts or warps.
Salvador · Project Manager
During: August 14, the caps going on the landing.
How the landing is built
The landing is the same pavers as the driveway, set on the same compacted base, with charcoal bullnose caps on its outer edge. Under the caps, the riser starts as a full course of pavers at the door and shrinks until the caps sit flush with the driveway.
About 1,000 square feet of driveway
Our site measure came to 31 by 20 feet plus 21 by 17, about 977 square feet, plus the curve along the planter. The asphalt came out on August 5, and on August 11 the crew started laying Courtyard Stone's Gray-Charcoal blend at the house.
During: August 11, the first rows at the house.
During: August 14, half the drive laid.
After: August 19, the border along the planter.
Four sizes in one field
Angelus sells Courtyard Stone as a four-stone package: 5.90 by 5.90, 5.90 by 8.90, 8.90 by 8.90, and 8.90 by 11.90 inches. Laid mixed, the sizes keep a long driveway from reading as a grid.
A border on every edge
A charcoal band frames the whole field: along the planter curve, at the low stucco wall, around the landing, and where the pavers meet the concrete apron at the sidewalk. Interlocking pavers need a fixed edge or the field slowly spreads, and the border course is where that edge is held.
During: August 19, the border turning at the wall.
After: the border at the concrete apron.
During: August 14, the side walk going in.
The side walk
Beside the house, the old asphalt ran right up to the wall. Now a paver walk runs down that side with its own charcoal border.
The same summer: a new exterior
Under a second contract, the house got new shingle siding, a black slate ledger stone base, and paint. The pavers went in first, with the walls still in building paper. At the city's inspection of the wall work, the inspector asked for flashing at the base of the walls; we added it before sign-off.
After: August 19, pavers done, walls in building paper.
After: September 25, the new exterior over the same pavers.
Build log
Two Weeks of Pavers, Start to Finish
Tue, Jul 15
Contract signed About 1,000 square feet of Angelus pavers.
Tue, Jul 22
Site measure 31 by 20 and 21 by 17 feet, plus the curve.
Thu, Jul 24
Samples Courtyard Stone in Gray-Charcoal, from the Angelus book.
Tue, Aug 5
Tear-out The asphalt driveway broken out and hauled away.
Mon, Aug 11
Pavers start The first rows go down at the house.
Thu, Aug 14
Field and landing Half the drive laid, the landing caps and side walk going in.
Tue, Aug 19
Pavers done Driveway, border, landing, and side walk finished.
Thu, Sep 25
Exterior done New siding, stone base, and paint over the pavers.
Project specs
Pavers
Angelus Courtyard Stone, about 1,000 sq ft
Color
Gray-Charcoal blend
Sizes
Four-stone package, squares and rectangles
Border
Charcoal band on every edge
Entry
Landing with a full step at the door, flush at the far end
Caps
Charcoal bullnose
Removed
Asphalt driveway, tiled step, plywood ramp
Crew
Licensed paver subcontractor, managed by Hybrid Renovations
La Mirada has a lot of driveways like this one: old asphalt, a step at the door that came with the house, and edges crumbling into the planters. We see the same front yards in Whittier, Santa Fe Springs, and La Habra, and the same answer works there: a paver driveway and entry built as one job.
If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.
Yes, and on this La Mirada job the asphalt came out first: it was cracked from the street to the walls, and cracks in a base carry up into whatever sits on it. The Concrete Masonry and Hardscapes Association does publish a guide spec for laying pavers over existing asphalt, but a broken base is the wrong place to start. Under a residential driveway, CMHA calls for at least 6 inches of compacted base over well-drained soil, and more on wet or weak soil.
Often, yes, if there's room to run the slope out. Here the landing runs along the front wall: a full step at the door that tapers until it sits flush with the driveway at the far end, so the entry needs no ramp. It still needs a fall for rain, and CMHA's minimum slope for pavers is 1.5 percent, so we measure the threshold height and the run on site before we lay it out.
They need an edge that can't move; the border is how it looks. Interlocking pavers stay locked only while their edges hold, which is why CMHA rules out thin landscape edging and calls for steel, aluminum, concrete, or plastic restraint made for pavers, spiked into the base and not the soil. On this driveway, a charcoal border course runs every edge: along the house, the low stucco wall, the planter, and the concrete apron.
For a home driveway, yes. Angelus makes Courtyard Stone 60 mm thick, about 2 3/8 inches, and CMHA rates 60 mm pavers for residential driveways, with 80 mm the usual pick for pavements under regular vehicle traffic (Angelus offers Courtyard Stone in 80 mm as a special order). The pieces are close to square too, and that matters under tires: CMHA keeps long, narrow units, 4 to 1 or longer, out of vehicle areas.