About This Project

Five Questions at the Walkthrough

Remodeled hall bathroom with a curbless shower, reeded glass panel, and fluted walnut vanity by Hybrid Renovations, Cerritos
After: a curbless shower where the tub stood, lit by a wider window.

Linh T. met us in this 1972 Cerritos hall bath with five questions on a sticky note. The room was last redone around 2004 with builder-grade parts. Here is how each question was answered on the job.

Original hall bathroom with a fiberglass tub-shower, a two-piece toilet, and a white thermofoil vanity, Cerritos
Before: a fiberglass tub, a tank toilet, and a thermofoil vanity.

Can the window be bigger?

The old window was a small vinyl double-hung, and the room ran on the ceiling light at noon. A wider window means a wider hole in an exterior wall that carries the roof, so this one started with a permit and a header.

We shored the ceiling, cut the opening wider, and set a new 4x10 header on new jack studs. The frosted casement sits in a sloped sill pan, with the sides and head flashed so water runs out, not in. Outside, the stucco was patched in three coats and painted to match.

Six-panel door, toggle switch, chrome towel bar, and a white double-hung window in the old bathroom, Cerritos
Before: a double-hung window and a towel bar.
Shaker door with a robe, a heated towel rail, and the wider frosted casement window by Hybrid Renovations, Cerritos
After: a wider casement and a heated towel rail.

Can the tub go, curb and all?

A curbless shower has to slope to its drain while its entry stays level with the room. On a concrete slab, the only way to get that slope is down. We saw-cut the slab across the old tub's footprint, broke it out, and moved the drain to a linear drain along the back wall.

How the shower floor went in

  1. Cut and trench. The shower area and the new drain line, about two inches below the old floor.
  2. Drain first. A brushed nickel linear drain set to the finished floor height, its trap below the slab.
  3. One slope. A mortar bed falling a quarter inch per foot to the back wall, level side to side.
  4. Waterproof it all. Two coats of liquid membrane on the floor and walls, lapped onto the drain flange and checked for thickness.
  5. Flood test. Water held over the whole base for 24 hours before the first tile.
White fiberglass tub-shower insert under a curved rod and waffle curtain, with beige dotted floor tile, before, Cerritos
Before: a fiberglass insert behind a curtain.
Curbless shower wall with a lit niche, a teak fold-down seat, reeded glass, and a eucalyptus bundle, by Hybrid Renovations
After: tile, glass, and a fold-down teak seat.
Cream and taupe checkerboard floor tile meeting a brushed nickel linear drain at the curbless shower entry, Cerritos
Detail: the floor runs straight to the drain.

Because the floor slopes one way, the same 12-inch checkerboard runs from the door into the shower without an angled cut. The fixed glass is clear above and reeded below, and the seat folds up on blocking set into the wall before tile.

Joseph Canchola, project manager at Hybrid Renovations

In a slab house, curbless means a saw. You can't build the slope up without building a step, so the floor comes down instead. Most of the work in this room is under the tile.

Joseph CancholaProject Manager

Can the toilet hang on the wall?

A wall-hung toilet keeps its tank in a steel carrier inside the wall, and a standard 2x4 wall is too shallow for it. We built the wall behind the toilet out to six inches, bolted the carrier to the slab and the studs, and moved the drain into the wall with a second short cut in the concrete.

Front view of the old two-piece toilet, its base ringed with yellowed caulk, against a tan wall and beige tile, Cerritos
Before: a tank toilet and a stained caulk ring.
Wall-hung toilet with a brushed nickel dual-flush plate under a lit niche by Hybrid Renovations, Cerritos
After: a wall-hung bowl and a nickel flush plate.
Arched niche glowing with a warm LED strip, travertine-look tile, a trailing pothos, and a framed botanical print, Cerritos
Detail: the arched niche over the toilet.

The deeper wall paid twice

The depth that holds the tank also holds a niche: the arch above the toilet is five and a half inches deep, lined with the shower's tile and lit by a warm LED strip. The flush plate below it is the service door. The valves come out through it, so a repair never means cutting tile.

I asked for a bigger window and no more tub. What I notice every morning is that there's nothing to step over.

Linh T.Homeowner, Cerritos

Will a floating vanity stay put?

A vanity that hangs off the wall is only as strong as what's behind it. Before drywall, we set 2x10 blocking between the studs at mounting height and raised the supply and drain lines for a cabinet with no floor under it. The quartz top went on after the cabinet was screwed to that blocking.

White thermofoil vanity with a cultured marble top, a frameless mirror, and a three-light bar before the remodel
Before: thermofoil, cultured marble, and a light bar.
Floating fluted walnut vanity with a quartz top under a backlit capsule mirror by Hybrid Renovations, Cerritos
After: fluted walnut, quartz, and a backlit mirror.
Quartz vanity top with an undermount sink, a brushed nickel faucet, an amber soap pump, and a lit candle, Cerritos
Detail: an undermount sink and a brushed nickel faucet.

Can it feel bright without more fixtures?

The wider window does most of it. The rest is light built into the walls: a warm LED strip in each niche, a backlit mirror wired to its own box behind the glass, and two recessed lights, all on dimmers. The shower niche's strip is rated for wet locations, and its driver sits where it can be reached. A quiet fan with a humidity sensor runs itself after a shower, and the heated rail has its own switch.

Long recessed shower niche with a warm LED strip, amber bottles, and a sea sponge, built by Hybrid Renovations, Cerritos
Detail: the shower niche, lit along its top.
Brushed nickel heated towel rail with a white towel beside the Shaker door and its robe, by Hybrid Renovations
After: the heated rail beside the door.

Build log

Six weeks, slab to final inspection

  • Week 1

    Protection and demo. Dust wall at the door; tub insert, tile, and vanity out; cut lines marked on the slab.

  • Week 2

    Concrete and drains. Shower area and trenches cut, linear drain and in-wall toilet drain run. Underground plumbing inspection passed.

  • Week 3

    Window and framing. Opening widened, header and window set; toilet wall built out, niches framed, blocking for the vanity, seat, and glass. Framing inspection passed.

  • Week 4

    Shower base and walls. Mortar bed sloped, membrane on, 24-hour flood test; drywall, plaster, and the stucco patch outside.

  • Week 5

    Tile. Porcelain on the shower walls, checkerboard from the door into the shower.

  • Week 6

    Finish. Glass, vanity, toilet, mirror, lights, and towel rail. Final inspection passed.

Project specs

Room
About 10 by 9 feet, single story, slab on grade
Shower
Curbless, slab lowered about two inches, linear drain at the back
Waterproofing
Liquid-applied membrane, two coats, 24-hour flood test
Wall tile
24x48 travertine-look porcelain, honed, laid horizontally
Floor
12x12 honed porcelain checkerboard, cream and taupe
Glass
Fixed panel, clear above, reeded below, nickel frame and towel bar
Toilet
Wall-hung bowl, in-wall tank and carrier, dual-flush plate
Vanity
Floating fluted walnut, quartz top, undermount sink
Window
Wider frosted casement, new header, sloped sill pan
Lighting
Backlit mirror, LED niche strips, recessed light, dimmers
Comfort
Heated towel rail, quiet fan with a humidity sensor

The finished bath carries our workmanship warranty in writing. We build bathroom remodels and curbless showers across Los Angeles County, including Artesia, Lakewood, and Norwalk.

The service behind this project

Looking for a bathroom remodeling contractor in Los Angeles County?

  • Licensed and insured, CSLB #1085596
  • Workmanship warranty

Frequently asked questions

Thinking about a project like this?

If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.

Yes, by lowering the slab where the shower goes. The concrete is saw-cut and broken out in the shower's footprint, the drain is moved, and a new, lower base is built so the floor can slope to the drain while the entry stays level with the room. Post-tensioned slabs need their cables located before any cutting, and some can't be cut at all, so we check the slab type first.

Yes. A wider opening in an exterior wall changes the framing, so it needs a new header, a building permit, and a framing inspection before the wall closes. Even a same-size window replacement often needs a permit in California because of the energy code. The stucco around a new opening is patched and painted as part of the job.

Usually. The tank and its steel carrier need a wall about six inches deep, so a standard 2x4 wall is built out, and the drain moves from the floor into the wall. In a slab home that means a short trench in the concrete. Once it's in, the tank's valves are serviced through the flush plate, so a repair never means opening tile.

With a linear drain, yes. A linear drain lets the shower floor slope in one direction, so a 12-inch tile can lie flat without the angled cuts a center drain needs. Choose a tile its maker rates for wet interior floors, usually listed as a DCOF of 0.42 or higher, in a honed or matte finish.

Still have questions?

Mon–Sun · 7 AM – 7 PM

FREE ESTIMATE

Get Your Free Estimate

We come to your home, look at the project, and give you a free, written estimate with no obligation. Construction, remodeling, and renovations across Los Angeles and Orange County.

  • Licensed and insured, CSLB #1085596
  • Free, whether or not you hire us
  • Same-day scheduling available
  • Measured on site, priced in writing
(562) 903-3955

Prefer to call? We answer 7 AM – 7 PM, Mon–Sun.

Tell us about your project