Primary Bath Remodel with a Walk-In Shower in Yorba Linda
August 2026
Yorba Linda
A 1991 primary bath in Yorba Linda, rebuilt to the studs. We moved the toilet off the window wall, built a tiled walk-in shower where it stood, and traded the tub-shower combo for a freestanding tub.
The window over the toilet looked into a stand of banana plants. For 35 years the nicest view in the room belonged to the toilet, and the homeowners wanted it back.
Nothing in the 1991 bath was broken. The raised-panel vanity, the cultured marble top, and the tub-shower combo with its single blue stripe all worked. They just meant stepping over a tub wall every morning and keeping towels in the hall closet. The list was short: a real walk-in shower, a tub worth soaking in, and storage.
Before: the toilet under the left window, a tub-shower under the right.
After: the same spot, with that window now inside the walk-in shower.
The layout question: where does the shower go?
Considered
A shower in the old tub alcove with the toilet left in place. Simple plumbing, but no tub.
Chosen
Move the toilet nine feet, put the shower under the left window, and a freestanding tub under the right.
Why: the room had space for both. The toilet was just in the wrong spot.
Before the saw touched the slab
What we found
A stamp in the garage read post-tensioned slab: steel cables under roughly 33,000 pounds of tension each. Nick one with a saw and you can weaken the whole slab.
What we did
Dust walls and a HEPA fan went up first. Then a ground-penetrating radar scan, every cable marked in paint, and both trenches routed between them, at least eight inches clear.
You don't guess with post-tension cables. Two hours of scanning that nobody ever sees is the most important part of a slab job.
Angel Valle · Project Manager
Moving the toilet nine feet
We set the new flange 12 inches from the finished wall, not the stud. Board and tile add almost an inch, and a stud measurement leaves a tank that won't sit flat. The new three-inch line falls a quarter inch per foot, with a cleanout a plumber can reach. The trench patch got epoxied rebar dowels and a vapor barrier, and the floor an uncoupling membrane, so the old cut line never cracks a tile.
Scope change: cracked cast iron
Under the old flange, the cast-iron drain had a cracked hub that had been seeping into the soil. We replaced six feet with ABS, which added one day, and showed the homeowners the cracked piece.
A shower built to stay dry
Before: the toilet nook behind a stub wall.
After: the same window, inside the shower.
Detail: the floor and bench slope to the drain.
How the shower was built
1Valves deep and by the door. Set for half-inch board plus tile so the trims sit flush, by the glass so you can start the water without stepping in.
2Block before board. Solid wood wherever a glass hinge or a future grab bar lands.
3Waterproof every seam. KERDI-BOARD, banded seams and corners, sealed screws, and membrane wrapped into the window opening.
4Slope, then flood test. Floor, bench, and niche shelf all drain, and the pan held water for 24 hours before any tile.
5Lay out from the niche. The niche sized to the tile, the valves on a grout line, and no slivers at the corners.
Why the corners get silicone, not grout
Walls and floors move a little, and not together. Grout in a corner cracks along that line and lets water in. Color-matched silicone at every change of plane flexes instead. It is in the tile industry's own installation standard.
What we found
The window we kept now sat in a wet wall: 38 inches off the floor, a painted wood sill, and too close to the shower floor for regular glass under California code.
What we did
A tempered sash in the same size and grid, membrane wrapped into the opening, and a sloped tile sill so water runs back into the shower.
Detail: flush trims by the door, the niche sized to the tile.
Detail: hinges screwed into blocking, sealed clean.
Tile, vanity, and tub
The 12x24 porcelain went down at a one-third offset, not halfway, so slightly bowed tile centers never meet, with leveling clips on every joint. Wet-area tile was back-buttered for at least 95 percent coverage, and each morning we pulled one fresh tile to check its back.
Before the walls closed, the vanity drains moved to the new sink centers and up high enough to clear the drawers, so the center drawer stack runs full depth. Blocking went in behind the mirrors and lights.
Before: one long mirror, two molded sinks.
After: a 72-inch Shaker double vanity with a quartz top.
The joint everyone looks at
The backsplash caulk line runs the full width at eye level. We tape both edges, run it in one pass, tool it once, and pull the tape before it skins.
The freestanding tub was delivered before the slab cut, so we marked its drain from the tub itself; plenty of them drain off-center. Outside the shower: moisture-resistant drywall, PVC board-and-batten that won't swell, wallcovering primer under the paper, and a humidity-sensing fan ducted outside.
Before: the tub-shower combo.
After: a freestanding tub on the same window.
After: the new linen tower by the door.
The details that never show up in a photo
Radar scan before any slab cut
Toilet rough-in from the finished wall
Doweled patch under an uncoupling membrane
Blocking behind every hinge and grab bar spot
95 percent mortar coverage in wet areas
Silicone, not grout, at every change of plane
Build log
Five weeks, demo to final inspection
Week 1
Protection, demo, slab. Dust walls up, tear-out to the studs, radar scan, slab cut, cast iron replaced.
Waterproofing and tile. Slab patch and membrane, shower waterproofing, flood test, then tile.
Week 4
Cabinets and trim. Vanity, quartz, linen tower, board-and-batten, wallpaper.
Week 5
Glass and fixtures. Glass installed eight days after templating, fixtures set, final inspection passed.
Project specs
Room
About 11 by 14 feet
Slab
Post-tensioned, radar-scanned before cutting
Toilet rough-in
12 inches from the finished wall, new 3-inch ABS line
Shower
5 by 4 feet, tiled bench, recessed niche, thermostatic valve
Tub
67-inch acrylic freestanding, deck-mounted filler
Vanity
72-inch white Shaker double, white quartz top
Tile
12x24 gray-vein porcelain at a one-third offset, 1x2 mosaic shower floor
Waterproofing
Schluter KERDI-BOARD, KERDI-BAND, KERDI-DRAIN; DITRA on the floor
Glass
3/8-inch clear tempered, polished chrome hardware
Ventilation
150 CFM fan on a humidity sensor, ducted outside
24working days
9 ftof drain moved
212sq ft of tile set
We said we'd do the bathroom someday for about ten years. What surprised us was how calm the job was. Angel texted us every afternoon with what got done and what was next.
Diane R. · Homeowner, Yorba Linda
The finished room carries our workmanship warranty in writing. We run primary bath remodels like this one across north Orange County, including Placentia, Brea, and Anaheim Hills.
The service behind this project
Looking for a bathroom remodeling contractor in Orange County?
If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.
Most primary bath remodels we run take four to six weeks on site. This one took 24 working days, including a slab cut, a rough and a final inspection, a 24-hour shower flood test, and an eight-day wait for the shower glass, which is cut to measurements taken after the tile is set. Keeping the existing layout usually takes about a week off.
Yes, as long as the cables are located first. We have the slab scanned with ground-penetrating radar, mark every cable, and route the trench between them, then run the new drain at a quarter inch of fall per foot and pass the city's rough plumbing inspection before the slab is patched. Many Orange County tract homes built since the late 1970s sit on post-tensioned slabs, and a stamp in the garage usually says so.
From the finished wall. A standard rough-in puts the center of the toilet flange 12 inches from the wall surface the tank will sit against, after the backer board and tile are on. Those layers add close to an inch, so a flange set 12 inches from bare studs can leave a tank that won't sit flat against the wall. We measure every new flange to the finished face.
Tile and grout are not waterproof, so the membrane behind them does the work. We use a bonded system like Schluter KERDI on the walls, bench, and floor, seal every seam, corner, and screw, slope the floor and bench toward the drain, and flood test the pan for 24 hours before any tile goes on. Silicone at every inside corner keeps grout from cracking and letting water in later.
We come to your home, look at the project, and give you a free, written estimate with no obligation. Construction, remodeling, and renovations across Los Angeles and Orange County.