A primary bath remodel in a 1991 Mission Viejo home. We traded a tiled tub deck for an arched plaster alcove and a freestanding tub, built a tiled shower, and added a makeup counter between the sinks.
This primary bath on the second floor of a 1991 Mission Viejo home was all original: honey oak, almond cultured marble, floral wallpaper, a tub dropped into a tiled deck, and a plastic stall behind brass-framed glass. The owners wanted to keep the room's footprint and its window, and change everything else. Most of the craft went into what you can't see.
Before: oak, wallpaper, and a tiled tub deck.
After: the same window, in a new room.
We kept the window and the walls it sits in. Everything else came out, so we could put the plumbing, the structure, and the air where the new room needs them, instead of working around 1991.
Angel Valle · Project Manager
Under the old tub deck
Before: a drop-in tub in a box of tile.
The old tub sat in a box of almond tile, with its brass faucet set into the deck and no access panel anywhere. When the deck came apart on day two, the plywood under it was dark and soft.
What we found
The deck faucet's supply fitting had been weeping into the deck for years. About 12 square feet of subfloor had come apart in layers, and nothing under the old tub was built to carry a freestanding one.
What we did
We cut the plywood back to sound wood and replaced it with 3/4-inch tongue-and-groove plywood, glued and screwed. Solid blocking went between the joists under the tub's feet, because a filled freestanding tub puts its whole weight on a few square inches.
Building the arch
After: the arched alcove, around the original window.
How the arch went in
1Clear the opening. The flat soffit came down to the framing, and we confirmed the opening wasn't carrying a load.
2Add a plumbing wall. A new 2x4 wall in front of the window wall holds the filler's valve, so no supply line runs in the exterior wall.
3Cut the curve once. Both sides of the arch come from one plywood template, so they match exactly.
4Bend, bead, and skim. Bendable drywall over the ribs, a vinyl arch bead on the edge, and a skim coat to a smooth curve.
5Frame the niches. Two small stacked niches on each side were framed before the drywall, not cut in after.
Detail: the filler, set to the tub's rim.
A filler on the wall
A floor-mounted filler would have meant cutting into the subfloor we had just rebuilt. On the wall, it keeps the floor clear around the tub and its valve stays in the new inside wall.
Spout height, set before the wall closed
We set the tub on the finished floor first, measured its rim, and roughed in the valve so the spout lands inside the bowl with clearance above the rim. Guessing from a drawing is how fillers end up splashing the floor.
A tiled shower instead of a stall
Before: a one-piece acrylic stall.
After: tile, frameless glass, and a bench.
Detail: rain head, handheld, one valve.
In place of the stall: a sloped mortar bed, a low curb, and a bonded waterproof membrane over every wall, the bench, and the niche. Before any tile, we plugged the drain, filled the pan, and left it for 24 hours to prove it holds water.
The cream handmade-look tile runs to the ceiling. The bench and the niche shelves pitch toward the drain, and the glass was measured only after the tile was set, because tile adds thickness no drawing shows.
Scope change: the room's first exhaust fan
The old bath had only the window for ventilation, and the wallpaper seams near the shower had lifted from years of steam. We added a fan ducted out through the roof, on a humidity sensor, so it runs whenever the room needs it. It added one working day.
A vanity for two people at once
Before: one long counter and a bulb strip.
After: two sinks and a seat between them.
One long counter, or a place to sit?
Considered
A continuous 36-inch counter with cabinets between the sinks
Chosen
A makeup counter with knee space and a stool
Why: The owners get ready at the same time. A seat at the counter, with its own drawer, keeps hair tools and makeup off the sink counters.
After: a widespread faucet in honed quartzite.
After: the makeup counter and its stool.
The top is honed Taj Mahal quartzite, which takes heat and resists etching better than marble. Pleated-shade sconces at face height replaced the bulb strip, so the light lands on faces instead of the tops of heads.
Walls, ceiling, and floor
The wallpaper had been hung on bare drywall with no primer, so it pulled the drywall's face paper off with it. We sealed the torn spots, skimmed every wall, and finished them in limewash. The popcorn ceiling went to a lab before anyone scraped it. The sample came back clear, so we wet-scraped it and skimmed it smooth.
Before: almond tile on the diagonal.
After: terracotta-look porcelain.
The floor is 8x8 terracotta-look porcelain, chosen over real terracotta, which needs sealing and stains. It sits on an uncoupling membrane over the new plywood, so small movements in the framing don't crack the tile.
24Working days on site
24 hrShower pan flood test
12 sq ftOf subfloor replaced
1stExhaust fan the room ever had
Build log
24 working days, demo to final inspection
Week 1
Protection and demo. Floors and stairs covered, dust wall at the door. Wallpaper, tub deck, stall, and vanity out. Leak and soft subfloor found; ceiling sample sent to the lab.
Week 2
Structure and rough-in. Subfloor and blocking, ceiling scraped, plumbing wall and arch framed, valves roughed in, fan ducted. Rough inspection passed.
Week 3
Shower and walls. Mortar bed, membrane, and the 24-hour flood test. Arch bead and skim coat on every wall.
Week 4
Tile and vanity. Shower and floor tile. Vanity set and the quartzite templated.
Week 5
Finish and final. Quartzite, tub, filler, limewash, sconces, then the glass. Final inspection passed.
Project specs
Room
About 11 by 13 feet plus the tub alcove, second floor
Alcove
Arched plaster, new plumbing wall, two niches each side
Tub
Oval freestanding tub, matte white, on new blocking
Filler
Wall-mounted, brushed brass, two lever handles
Shower
Mortar bed, bonded membrane, 24-hour flood test
Shower tile
Cream 4x4 handmade-look ceramic, to the ceiling
Glass
3/8-inch tempered panel and door, brass hinges
Vanity
Rift white oak double vanity with a makeup counter
Counter
Honed Taj Mahal quartzite
Walls
Limewash over a full skim coat
Floor
8x8 terracotta-look porcelain on an uncoupling membrane
Ventilation
New fan ducted to the roof, humidity sensor
After: from the alcove back toward the entry.
The finished bath carries our workmanship warranty in writing. We handle primary bathroom remodels across South Orange County, including Lake Forest, Laguna Hills, and Rancho Santa Margarita.
The service behind this project
Looking for a bathroom remodeling contractor in Orange County?
If this project has you picturing your own home, you're not alone. These are the questions we answer most often for homeowners deciding to move forward, so you know exactly what working with us looks like.
Usually, yes. An arch is framed into an opening that isn't carrying a load, with plywood ribs cut from one template, bendable drywall, and an arch bead on the edge. If the opening does carry a load, a header goes in first. On this job the arch and its niches took about three working days of the schedule.
In most homes, yes, once the floor under it is checked. A filled tub with someone in it puts several hundred pounds on a few small feet, so we open the floor, replace any soft plywood, and add solid blocking between the joists where the tub will stand. The drain also has to land between joists, which we confirm before ordering the tub.
Neither is better everywhere. A wall-mounted filler keeps the floor clear and its valve inside a wall, but it needs a wall right at the tub and a spout height set before the wall closes. A floor-mounted filler suits a tub that floats in the room, and its lines run under the floor.
Yes. It has the warm color of terracotta without the upkeep: real terracotta is porous, needs sealing, and stains, while porcelain absorbs almost no water. Set on an uncoupling membrane, it also handles the small movements of a second-floor wood floor without cracking.
We come to your home, look at the project, and give you a free, written estimate with no obligation. Construction, remodeling, and renovations across Los Angeles and Orange County.